Budget vs. actual
Reviewed by Jakob Schubert · Co-Founder, Basqo · 2026-11-05
Definition
Budget vs. actual compares planned values with the actual results of the same period and shows the difference, in absolute terms and as a percentage. Finance and HR controlling use it to see where costs deviate from the plan. For workforce costs, it sets the approved plan against payroll actuals, month by month, so deviations show up while there is still time to react.
Formula
Deviation in % = (actual − budget) × 100 ÷ budget (for costs, a positive result means spending above plan)
Key takeaways
- Budget vs. actual compares planned values with actual results for the same period: €52,000 against a budget of €50,000 is a deviation of €2,000, or 4 %.
- For costs, a positive deviation means spending above plan, so a report should name the direction instead of relying on the sign alone.
- Budget vs. actual shows where a gap is, and variance analysis explains why it happened.
- For workforce costs, both sides need the approved plan version, the payroll actuals of the month and the same cost types.
How do you calculate budget vs. actual?
Subtract the budget from the actual value of the same period. The result is the absolute deviation. Multiply it by 100 and divide it by the budget to get the deviation in percent.
Example with illustrative numbers: a team plans 10 FTE at €5,000 a month each, so €50,000 in monthly workforce costs. The payroll actuals for the month show €52,000.
Item | Amount |
|---|---|
Budget | €50,000 |
Actual | €52,000 |
Deviation | €2,000 |
Deviation in % | 4 % above budget (2,000 × 100 ÷ 50,000) |
The result shows where the gap is and how large it is. It doesn’t say why. Finding the cause is the job of the variance analysis.
How do you read a budget vs. actual deviation?
Sign: for costs, a positive deviation means spending above plan. For revenue, it means results above plan. A report should therefore name the direction (“above budget”, “below budget”) instead of relying on the sign alone.
Absolute and percent: read both together. The same percentage means a few thousand euros in a small team and a much larger amount across the whole workforce budget.
Timing: payroll actuals are final only after the payroll run. A comparison made before the month is closed shows gaps that disappear again a few days later.
What has to match between budget and actuals?
A comparison is only as reliable as its inputs. Both sides need the approved plan version, the same cost types and the same structure: positions, teams, entities and the same FTE basis.
Mismatched cost types are easy to miss. If the plan holds gross salaries only and the actuals include employer contributions, the comparison shows an overrun that nobody caused. That gap is not small: in Germany, employers paid an extra €29 in non-wage labor costs on top of every €100 of gross earnings in 2024.
What is the difference between budget vs. actual and variance analysis?
Budget vs. actual finds the gap. Variance analysis finds the cause, for example more FTE than planned, a different start date or a pay change. The comparison tells HR controlling and Finance which lines need a closer look, and the variance analysis explains them. Both run together in monthly reporting, which is why the two terms are often mixed up.
Why does budget vs. actual matter for workforce costs?
Workforce costs are often one of the largest cost blocks, and they change through many small decisions: hires, leavers, changes in working hours and pay rises. A monthly comparison shows deviations while there is still time to react, for example by moving a start date or updating the forecast. That makes budget vs. actual a core routine of HR controlling, next to headcount reporting and the forecast.
Common mistakes
- Comparing against an old plan instead of the approved version, so the deviation measures plan changes instead of spending.
- Mixing cost types: a plan with gross salaries only against actual costs including employer contributions, which shows an overrun that isn’t real.
- Looking only at the total and not at the position or team, so an overrun in one team hides a saving in another.
In Basqo
How to run budget vs. actual for workforce costs
In a spreadsheet, the plan and the payroll actuals sit in different files, so each month starts with copying data and matching cost types by hand. Basqo syncs the HRIS on an ongoing basis, brings in payroll actuals monthly for reconciliation and compares them with the approved plan version. The variance analysis goes down to the position, including cost drivers, and the monthly development by cost type and FTE shows whether a gap comes from people or from pay. More on the process: why people teams need a month-end close.
At Parloa, monthly reporting is more than 75 % faster with Basqo.
Forecast & controlling in BasqoFrequently asked questions
It means comparing planned values with the actual results of the same period. The difference shows where costs or revenue deviate from the plan.
The deviation is actual minus budget. Multiplied by 100 and divided by the budget, it gives the deviation in percent.
No. Budget vs. actual shows where and how far results deviate from the plan, and variance analysis explains why.
Many Finance teams review it monthly, once payroll actuals are available. The right rhythm depends on how often the plan changes.
Comparing budget and actual looks back: it sets the plan against what was actually spent. Comparing plan and forecast looks ahead: it compares the plan with the latest expected result for the rest of the year, so deviations show up before they happen.